Ask a principal why a year was tight and the answer is usually about fees: a project was underpriced, a client pushed back, a phase ran long. Those are real, but they show up in two numbers you can watch every month instead of discovering at year end.
Utilization: how much of the week went to client work
Utilizationbillable hours ÷ available hours
Available hours are the hours someone could work in the period after holidays and leave. If a designer has 150 available hours in a month and records 120 on billable project phases, their utilization is 80%.
There is no single right target. A junior designer might sit near 85–90%; a principal who sells work, manages people and reviews drawings might be at 40–50% and still be doing their job well. What matters is that each role has a target, and that you notice when people drift away from it for several weeks in a row.
Realization: how much of that work you were paid for
Realizationamount billed ÷ standard value of the time
Standard value is billable hours multiplied by each person's bill rate. If a phase used $40,000 of time at standard rates and you invoiced $32,000 for it, realization on that phase is 80%. The missing $8,000 is a write-down, whether anyone decided it or not.
On a fixed-fee project, realization is how you see overruns in dollars. On hourly work, it shows the time you chose not to bill. Some firms also measure collected realization, using cash received instead of invoices issued, which catches the invoices that are never paid.
Why you need both
High utilization with low realization means the team is busy on work that does not pay: scope creep, rework, or fees set too low. High realization with low utilization means the work pays, but there is not enough of it, or too much time goes to overhead.
- Review utilization by person monthly, against a target for their role.
- Review realization by project phase, not only by project, so you can see where the overrun started.
- Decide write-downs on purpose, with a reason, rather than letting them happen at invoice time.
- Compare both numbers with the budget for the phase while there is still time to act.
In Issued For, the utilization report divides each person's approved billable hours by their holiday-adjusted capacity, and project reports compare approved time and fees with each phase's budget. Both start from the same approved timesheets your invoices use, so the numbers agree with each other.